ARDING & HOBBS
Clapham, London, SW4
Completion: |
August 2004 |
Client: |
Allders Department Stores Ltd |
Principal Contractor: |
Dean & Bowes |
Project Manager: |
BIS (Burgess Integrated Systems) Ltd |
Value: |
£100,000 |
Nature of Works: |
Restoration of existing three elevations; stonework and brickwork. Structural repairs to 1st floor Portland Stone cornice, involving removal of defective stone, treatment of oxidised structural steelwork, and design supply and fix of new replacement stone and stainless steel restraint fixings..
|
|
|
|
|
|
|